Lead Status & Order Status


Overview

A lead/Quote status is setup with a function, the function prompts an action within the system.

You can have as many statues as required. With the ability to update to different colours (this is displayed in your calendar).

If you have multiples statuses with the same function the status that is first in sequence is the status that will prompt that function when required.

Emails can be setup to send on status change see here for setup → Email Templates


To access these menu's select  Settings - Sales Settings, then at the top select the relevant tab or you can access the CSV by selecting Import Export Sales Settings



Lead Status



Lead status descriptionFunctionMeaning
1New LeadNot MeasuredNew lead, not yet seen by rep
2WonWonLead has converted to a sale
3LostlostLead was not converted to sale
4CancelledCancelledCancelled appointment
5Follow upFollow upFollow up appointment booked from quote
6General AppointmentGeneral AppointmentAny appointments that don't fit into the categories above
7Private AppointmentPrivate AppointmentDays off, sick days, general appointments - This status works differently to the status's above and can be created in the calendar or import/export function

Order Status




Order status descriptionFunctionMeaningExample of Order (click to enlarge image)
1QuoteQuoteQuote (not yet accepted)

2Needs Minimum Deposit ApprovalDeposit approval neededDeposit added and Requires min deposit approval

3Discount Approval NeededDiscount approval neededDiscount exceeded max discount and requires discount approval 

4Declined (Lost)Lost

quote - declined never accepted


5Accepted (Needs Processing)Needs Processingmanual process is required for a quote or rework that has been accepted

6Needs Remote FinalizingNeeds Remote order FinalizeAccepted Buz 2 Buz needs finalizing from supplier



7Ordered from SupplierNeeds Remote order FinalizeAccepted Buz 2 Buz finalized from supplier

8Pending (Waiting for) Check MeasureWaiting for check measureAccepted waiting for check measure

9Work in ProgressWork in progressAccepted didn’t require approval or has been approved and either has no check measure or check measure has been completed)

10Installed (To Be Invoiced)To be invoicedInstalled not yet invoiced

11CancelledCancelledAccepted then order Cancelled

12Invoiced (Complete)CompleteInvoiced/completed (Note - a copy of the invoice is not automatically emailed to the client in the order summary screen, this is a manual process) Refer to the Bulk Invoicing help page for this feature.

13Credit NoteCredit NoteCredit note not an order applicable, applied to invoiced orders

14Credit Approval NeededCustomer Credit Approval NeededCredit Approval Needed exceeded max credit limit. More help on credit limits can be found here.

Example