BUZ follows the order sequence below:
Enter the order > Order is accepted > Check Measure is complete > Job Tracking > Dispatch

You can complete things out of order but it may affect the processes following it. The reason for this design is so that both your production and dispatch can be aware of any changes made and reduce reworks.

In this example below, the Installation line changes from Confirmed to Unconfirmed due to a new component being added.

Order 1000166.A is accepted by customer and waiting for check measure

Dispatch Scheduling - both lines (Installation and Check Measure are unconfirmed

Both Check Measure and Installation dates are confirmed

During Check Measure the order is edited and a new component is added and then Check Measure is completed

As the new component has a Job Tracking Line, this changes the overall Installation from Confirmed to Unconfirmed

Depending on your business requirements, you may not want the Installation/Dispatch status to change. In this instance, you will need to remove the Job Tracking Line from the Group.

To remove a Job Tracking Line from the Group, go to

Settings > Inventory Settings > Groups > select the relevant group with components > scroll down to Job Tracking (Default) and change this selection to none and save.

Please note, doing this will affect all items in the corresponding Group, hence if there is something that requires a Job Tracking Line, then you should move it to a separate Group or create a separate group for the product/component.